Power Restored for Planned Outage in Tecumseh

Power Restored for Planned Outage in Tecumseh


Approximate Number of Customers Affected: 6
Date of Power Outage: 2020-07-29 09:15
Municipalities Affected: Tecumseh
Location(s) within Affected Municipalities: LEMIRE ST
Cause of Outage: Scheduled Outage
Additional Details: REPLACED TRANSFORMER (TX10172)
Actual Time of Restoration: 2020-07-29 10:40
Duration of Outage: 85 minutes
Outage ID: 8417