Power Restored for Unplanned Outage in Amherstburg

Power Restored for Unplanned Outage in Amherstburg


Approximate Number of Customers Affected: 23
Date of Power Outage: 2020-03-07 20:32
Municipalities Affected: Amherstburg
Location(s) within Affected Municipalities: FRONT RD N, GORE ST, SANDWICH ST S, SEYMOUR ST
Cause of Outage: Overhead Transformer Switch
Additional Details: Blown transformer switch, crews replaced the switch to restore power.
Actual Time of Restoration: 2020-03-08 00:02
Duration of Outage: 209.65 minutes