Restored Power for Leamington report

Restored Power for Leamington report


Approximate Number of Customers Affected: 126
Date of Power Outage: 1/4/2020 5:55:00 AM
Municipality Affected: Leamington
Location within Area: STURGEON MEADOWS AVE, WORCHESTER AVE & ANFRED AVE
Cause of Outage: Foreign Interference Human
Additional Details: TRANSFORMER DAMAGED IN A MOTOR VEHICLE COLLISION. CREWS ARE GROUNDING LINES TO MAKE SAFE AND WORKING TO REPLACE DAMAGED TRANSFORMER.
Actual Time of Restoration: 1/4/2020 9:58:00 AM
Duration of Outage: 04:03:00

Update on Leamington Power Outage

Update on Leamington Power Outage


Approximate Number of Customers Affected: 126
Date of Power Outage: 1/4/2020 5:55:00 AM
Municipality Affected: Leamington
Location within Area: STURGEON MEADOWS AVE, WORCHESTER AVE & ANFRED AVE
Cause of Outage: Foreign Interference Human
Additional Details: TRANSFORMER DAMAGED IN A MOTOR VEHICLE COLLISION. CREWS ARE GROUNDING LINES TO MAKE SAFE AND WORKING TO REPLACE DAMAGED TRANSFORMER.
Estimated Time of Restoration: 1/4/2020 12:00:00 PM