Archive for 6 April 2019

Restored Power for Tecumseh report

Restored Power for Tecumseh report


Approximate Number of Customers Affected: 34
Date of Power Outage: 4/6/2019 3:52:00 PM
Municipality Affected: Tecumseh
Location within Area: ST JACQUES ST, LARAMIE ST, FIRST ST & LESPERANCE RD
Cause of Outage: Switches
Additional Details: PART POWER ON 3 PHASE BANK DUE TO A BROKEN SWITCH. CREWS DEENERGIZED THE PRIMARY TO MAKE SAFE AND REPLACE THE SWITCH.
Actual Time of Restoration: 4/6/2019 7:35:00 PM
Duration of Outage: 03:43:00

Update on Tecumseh Power Outage

Update on Tecumseh Power Outage


Approximate Number of Customers Affected: 34
Date of Power Outage: 4/6/2019 3:52:00 PM
Municipality Affected: Tecumseh
Location within Area: ST JACQUES ST, LARAMIE ST, FIRST ST & LESPERANCE RD
Cause of Outage: Switches
Additional Details: PART POWER ON 3 PHASE BANK DUE TO A BROKEN SWITCH. CREWS HAVE TO DEENERGIZE THE PRIMARY TO REPLACE THE SWITCH SAFELY.
Estimated Time of Restoration: 4/6/2019 8:00:00 PM