Restored Power for Tecumseh report

Restored Power for Tecumseh report


Approximate Number of Customers Affected: 4
Date of Power Outage: 4/1/2019 6:29:00 AM
Municipality Affected: Tecumseh
Location within Area: RIVERSIDE DR E
Cause of Outage: Connection
Additional Details: SECONDARY CONNECTIONS FAILED CAUSING PART POWER, CREWS DEENERGIZED AND REPAIRED CONNECTIONS AT TRANSFORMER TO RESTORE POWER
Actual Time of Restoration: 4/1/2019 8:57:00 AM
Duration of Outage: 02:28:00

Power Outage for Tecumseh

Power Outage for Tecumseh


Approximate Number of Customers Affected: 4
Date of Power Outage: 4/1/2019 6:45:00 AM
Municipality Affected: Tecumseh
Location within Area: RIVERSIDE DR E
Cause of Outage: Connection
Additional Details: SECONDARY CONNECTIONS FAILED CAUSING PART POWER, CREWS ARE REPAIRING CONNECTIONS AT TRANSFORMER
Estimated Time of Restoration: 4/1/2019 10:00:00 AM