Essex Power – Restored Power for Tecumseh Report

Essex Power – Restored Power for Tecumseh Report


Approximate Number of Customers Affected: 40
Date of Power Outage: 2018-10-29 at 17:10:00
Municipality Affected: Tecumseh
Location within Area: CADA JASON CRT EDWATER MANNING
Cause of Outage: Unknown
Additional Details: DEFECTIVE MVI ISOLATED, DEFECTIVE UNDERGROUND CABLE ISOLATED, BLOWN ARRESTER REPLACED AND CREWS PERFORMED SWITCHING TO RESTORE POWER TO ALL CUSTOMERS
Actual Time of Restoration: 2018-10-29 at 22:55:00
Duration of Outage: 5 Hours and 45 Minutes

Essex Power – Update on Tecumseh Power Outage

Essex Power – Update on Tecumseh Power Outage


Approximate Number of Customers Affected: 40
Date of Power Outage: 2018-10-29 at 17:10:00
Municipality Affected: Tecumseh
Location within Area: CADA JASON CRT EDWATER MANNING
Cause of Outage: Unknown
Additional Details: POSSIBLE DEFECTIVE MVI UNIT OR UNDERGROUND CABLE, CREWS PERFORMING SWITCHING TO ISOLATE AND FEED CUSTOMERS FROM DIFFERENT LOCATIONS
Estimated Time of Restoration: 2018-10-29 at 23:30:00

Essex Power – Update on Tecumseh Power Outage

Essex Power – Update on Tecumseh Power Outage


Approximate Number of Customers Affected: 40
Date of Power Outage: 2018-10-29 at 17:10:00
Municipality Affected: Tecumseh
Location within Area: CADA JASON CRT EDWATER MANNING
Cause of Outage: Unknown
Additional Details: RESTORED POWER TO 20 CUSTOMERS REMAINING. 40 CUSTOMERS ON RED PHASE AND PART POWER TO COMMERCIAL CUSTOMERS, RED PHASE TRIPPING MVI CREWS WORKING TO FIND CAUSE
Estimated Time of Restoration: 2018-10-29 at 22:00:00

Essex Power – Update on Tecumseh Power Outage

Essex Power – Update on Tecumseh Power Outage


Approximate Number of Customers Affected: 60
Date of Power Outage: 2018-10-29 at 17:10:00
Municipality Affected: Tecumseh
Location within Area: CADA JASON CRT EDWATER MANNING
Cause of Outage: Unknown
Additional Details: BLOWN LINE FUSE CAUSE UNKNOWN CREWS INVESTIGATING
Estimated Time of Restoration: 2018-10-29 at 20:30:00

Essex Power – Restored Power for Leamington Report

Essex Power – Restored Power for Leamington Report


Approximate Number of Customers Affected: 40
Date of Power Outage: 2018-10-29 at 15:15:00
Municipality Affected: Leamington
Location within Area: FOUNDRY AND CLARK ST
Cause of Outage: Unknown
Additional Details: BLOWN LINE FUSE CAUSE UNKNOWN CREWS INVESTIGATING
Actual Time of Restoration: 2018-10-29 at 18:10:00
Duration of Outage: 2 Hours and 55 Minutes

Essex Power – Power Outage for Tecumseh

Essex Power – Power Outage for Tecumseh


Date of Power Outage: 2018-10-29 at 17:10:00
Municipality Affected: Tecumseh
Location within Area: CADA JASON CRT EDWATER
Cause of Outage: Unknown
Additional Details:
Crews Dispatched: Yes

Essex Power – Update on Leamington Power Outage

Essex Power – Update on Leamington Power Outage


Approximate Number of Customers Affected: 40
Date of Power Outage: 2018-10-29 at 15:15:00
Municipality Affected: Leamington
Location within Area: FOUNDRY AND CLARK ST
Cause of Outage: Unknown
Additional Details: BLOWN LINE FUSE CAUSE UNKNOWN CREWS INVESTIGATING
Estimated Time of Restoration: 2018-10-29 at 18:00:00

Essex Power – Power Outage for Leamington

Essex Power – Power Outage for Leamington


Date of Power Outage: 2018-10-29 at 15:15:00
Municipality Affected: Leamington
Location within Area: FOUNDRY AND CLARK ST
Cause of Outage: Unknown
Additional Details:
Crews Dispatched: Yes

7249 (Updated) – LEAMINGTON OUTAGE FOR TREE TRIMMING

Approximate # of customers : 75
Date of Outage : 10-26-2018 08:30 AM
Areas : A3-LEA
Estimated Restore Time : —
Details : ALL POWER WAS RESTORED ON ONTARIO ST, OAK ST E, ROBINSON ST, VICTORIA AVE S & WIGLE ST IN LEAMINGTON AT 3:25PM ON OCTOBER 26 2018.

7249 – LEAMINGTON OUTAGE FOR TREE TRIMMING

Approximate # of customers : 75
Date of Outage : 10-26-2018 08:30 AM
Areas : A3-LEA
Estimated Restore Time : 10-26-2018 03:00 PM
Details : WILL AFFECT 75 CUSTOMERS ON ONTARIO ST, OAK ST E, VICTORIA AVE S, WIGLE ST & ROBINSON ST