Archive for 5 June 2018

Essex Power – Update on Leamington Power Outage

Essex Power – Update on Leamington Power Outage


Approximate Number of Customers Affected: 25
Date of Power Outage: 2018-06-05 at 19:30:00
Municipality Affected: Leamington
Location within Area: MARBOROUGH MAYNARD
Cause of Outage: Tree Contact
Additional Details: BLOWN FUSE INSIDE TRANSFORMER, TREE CONTACT WITH STREET LIGHT WIRE CAUSED WIRE TO TANGLE UP WITH OPEN BUSS CAUSING SHORT CIRCUIT AND BLOWING FUSE INSIDE TRANSFORMER. CREWS WORKING TO CLEAR WIRE IN OPEN BUSS.
Estimated Time of Restoration: 2018-06-05 at 00:00:00

Essex Power – Power Outage for Leamington

Essex Power – Power Outage for Leamington


Date of Power Outage: 2018-06-05 at 19:30:00
Municipality Affected: Leamington
Location within Area: MARBOROUGH MAYNARD
Cause of Outage: Unknown
Additional Details:
Crews Dispatched: Yes