Archive for 6 October 2017

6500 (Updated) – LEAMINGTON OUTAGE TO REPLACE BROKEN SWITCH

Approximate # of customers : 18
Date of Outage : 10-06-2017 10:15 AM
Areas : A3-LEA
Estimated Restore Time : —
Details : ALL POWER WAS RESTORED ON WINDWOOD DR & SOUTHBRIDGE ST IN LEAMINGTON TO REPLACE THE BROKEN SWITCH AT 10:45AM ON OCTOBER 6, 2017.

6499 (Updated) – LEAMINGTON OUTAGE TO CHANGE TRANSFORMER

Approximate # of customers : 4
Date of Outage : 10-06-2017 10:15 AM
Areas : A3-LEA
Estimated Restore Time : —
Details : ALL POWER WAS RESTORED ON WINDWOOD DR & SOUTHBRIDGE ST IN LEAMINGTON FOR THE TRANSFORMER REPLACEMENT AT 12:10PM ON OCTOBER 6, 2017.

6500 – LEAMINGTON OUTAGE TO REPLACE BROKEN SWITCH

Approximate # of customers : 18
Date of Outage : 10-06-2017 10:30 AM
Areas : A3-LEA
Estimated Restore Time : 10-06-2017 11:30 AM
Details : WILL AFFECT 18 ADDITIONAL CUSTOMERS ON WINDWOOD DR & SOUTHBRIDGE ST.

6499 – LEAMINGTON OUTAGE TO CHANGE TRANSFORMER

Approximate # of customers : 4
Date of Outage : 10-06-2017 09:30 AM
Areas : A3-LEA
Estimated Restore Time : 10-06-2017 01:30 PM
Details : WILL AFFECT 4 CUSTOMRES ON WINDWOOD DR & SOUTHBRIDGE ST.